PROJECT DESCRIPTION

The Albert M. Higley Co. . served as the concrete and general trades contractor for the Cleveland Hopkins International Airport Concourse “D” project which included an interconnecting 730’ underground tunnel to the existing terminal building. The 2-story concourse included 12 jet bridges, 4 fingers for turbo prop airplanes, and an 80' tall control tower.

Client
Morse Diesel International

Architect
KCF/SHG & Robert P. Madison International

Size
170,000 SF

​Construction Value
$25 MM

​Project Completion
September 1999